Road projects and the overlay program
On December 11, 2025 the Committee awarded King George Road Phase II to Stilo of South Plainfield for $221,889.98 and Mountainview Road Phase I for $357,660.05, lowest of nine and ten bids, 4–0 with Committeeman Blick absent. Both ran on NJDOT Municipal Aid grants.
Mountainview Road Phase II went to Riverview Paving on June 18, 2026 at not more than $509,422.55 (Res. 2026-155, 5–0). Change orders added $79,690.15 to Mountainview Phase I on July 16 and $29,512.69 to King George on August 20.
The 24-street overlay contract with Carroccia Co. Contractors, not more than $945,800, was awarded May 14 (Res. 2026-152) and required a completed-roads report by September 30. Committeeman Croson said on August 20 the overlay was “almost complete.” LocalWhy has not reviewed the September 24 and October 22 minutes.