Data centers
The data-center prohibition
Ordinance 26-19, adopted 5–0 on June 18, 2026, prohibits data centers in every zone. At its May introduction, Committeeman Croson said there were no applications or plans.
What happens next
No further public step is scheduled in the records reviewed. The ordinance says it takes effect upon adoption, passage and publication; LocalWhy has not reviewed proof of publication.
Ordinance 26-19, adopted 5–0 by the Township Committee on June 18, 2026, prohibits data centers in every zone. It states that it takes effect upon adoption, passage and publication; LocalWhy has not reviewed proof of publication.
On April 16, 2026, Committeeman Croson raised “the impact of data centers on communities, including to noise and energy impacts”. He asked Township Attorney William Willard to research what Warren could do. Willard and Township Planner Katie Sarmad said they would draft an ordinance. At the May 14 introduction, Croson said there were “currently no applications or plans for a data center.”
The Committee introduced the ordinance on May 14. The vote was 4–1, with McCarey voting no. At the June 18 public hearing, two speakers from outside Warren addressed the Committee. McCarey said he supported prohibiting data centers. He questioned the wording of the standards. The hearing closed. The ordinance then passed 5–0.
Section 16-5.25(a)(7) adds “All Data Centers and any and all uses related to the same” to the uses prohibited in all zones. The ordinance removes data centers from the General Industrial district’s permitted uses and adds supplementary standards at §16-23.14 for any application: a 200-foot (OCR) separation from sensitive receptors, a 300-foot (OCR) building setback, sound studies by a certified engineer, a renewable-energy requirement, a heat-recovery system and a decommissioning bond.
The ordinance’s OCR text says a use “with a power density of 2 to 4W (OCR) or more per acre shall be considered a data center.” LocalWhy has not resolved whether it is a drafting error.
The Planning Board’s June 10, 2026 agenda listed the ordinance for review of Master Plan consistency. The minutes need a browser; LocalWhy has not reviewed the Board’s action.
Timeline
- Active Committee discusses data-center regulationCommitteeman Croson raised noise and energy impacts of data centers, referred to ordinances in other New Jersey municipalities and asked the Township Attorney to research options for Warren. Staff said they would draft an ordinance.
- Active Committee introduces data-center ban, 4–1Ordinance 26-19, defining data centers and prohibiting them in all zones, was introduced on a 4–1 vote. McCarey voted no; Blick, Croson, Deputy Mayor Kian and Mayor Fine voted yes.
- Resolved Committee adopts data-center prohibition, 5–0The Township Committee adopted Ordinance 26-19, 5–0, after a public hearing. The ordinance prohibits data centers in every zone and sets supplementary standards for any variance application.
Explainers
Documents
Ordinance 26-19: data centers defined and prohibited in all zones
Agenda, June 18, 2026 Township Committee meeting
Minutes, June 18, 2026 Township Committee meeting
Agenda, June 10, 2026 Planning Board meeting
Agenda, May 14, 2026 Township Committee meeting
Minutes, May 14, 2026 Township Committee meeting
Minutes, April 16, 2026 Township Committee meeting