Data centers
Data centers and the Greymark site (1200 Route 22)
The 2025 redevelopment plan for the Greymark Office Tract at 1200 Route 22 lists data centers as a permitted use. The Council adopted townwide data-center standards (Ord. 26-15) 3-0 on Sept. 3, 2026; the owner sued on Oct. 5, Patch reported; and on Oct. 15 the Council introduced #26-21 to remove data centers from the Greymark plan.
What happens next
Public hearing and final vote on Ordinance #26-21 at the Township Council meeting of Nov. 5, 2026, as set by the township's introducing resolution (#26-10-15-222). The Planning Board found #26-21 not inconsistent with the Master Plan on Oct. 27, 2026. The owner's suit over Ord. 26-15, as Patch reported it, is in Superior Court.
The Greymark Office Tract is about 28 acres at 1200 Route 22 East, at Adamsville Road North, with a medical office building at the front and homes on Adamsville Road, Woodside Lane and nearby streets around it. The Council designated it an area in need of redevelopment in December 2024 (TAPinto) and adopted a redevelopment plan for it by Ordinance 25-05 in April 2025. That plan lists data centers as a permitted use. According to the Mayor’s letter as Patch and TAPinto reported it, the owner sued in November 2022 over the township’s October 2022 ordinance removing warehouses as a permitted use; in July 2026 Councilman Kirsh and the Township Attorney said a warehouse application for the site was still before the Zoning Board, subject to that litigation. The Zoning Board’s records show that application (#23-011-ZB) carried several times in 2026. For Jan. 27 the minutes say it was “heard and is adjourned,” while the transcript has the Board attorney saying it would not be heard; its Sept. 22 agenda says the hearing “WILL NOT PROCEED TONIGHT.”
The subdivision. The owner’s preliminary major subdivision (App. 25-021-PB) proposed four lots where five exist, “with one of the proposed lots intended for use as a Data Center and three of the proposed lots for residential use,” per the Planning Board’s March 17, 2026 agenda. The Board’s April 21 agenda lists it as “Approved 3/17/26,” and on April 21 the Board adopted the memorializing resolution 6-0 (Bongiorno, Magura, Wang, Isla, Choudhury, Vescio; Atkins, Banga, Sikora and Mayor Moench not eligible; Pappas absent). The Council’s Aug. 20 minutes number it “25-02-PB.”
Ordinance 26-15. After residents spoke about data centers at Council meetings from May 18, 2026 on, the Council adopted Ordinance #26-15 on Sept. 3, 2026, 3-0 (Bucko, Kirsh and Geiger aye; Isla and Ring absent). Township Planner Katherine Sarmad said it defines a data center as two megawatts or more per acre and a hyperscale data center as 80 megawatts or more; it does not permit data centers anywhere, and sets standards (low-frequency noise, generators, water sources, renewable energy, waste-heat recovery) for any use-variance application. Township Attorney Christopher Corsini said that, “broadly speaking,” it would apply to 1200 Route 22.
In court. On Oct. 5, 2026, the owners (1200 Route 22 Land Investors, LLC and 1200 Route 22 Land Holdings LLC) sued the township and the Planning Board in Somerset County Superior Court, asking that Ord. 26-15 be declared invalid or unenforceable in the Greymark area, as Patch and TAPinto reported the complaint. Mayor Matthew Moench wrote to the owner’s representative that he had told township attorneys to return the 2022 warehouse case, SOM-L-1372-22, to active litigation.
Ordinance #26-21. On Oct. 15, 2026 the Council introduced #26-21, amending the Greymark plan, according to the township’s notice; as TAPinto described it, the ordinance removes data centers as a permitted use and lists them as prohibited. The township’s introducing resolution (#26-10-15-222) records the vote as 5-0 and sets the hearing for Nov. 5. On Oct. 27 the Planning Board found it not inconsistent with the Master Plan and recommended adoption. The final vote has not yet happened.
What residents can do. Speak at the public hearing on #26-21 (Nov. 5, 2026) and in public comment at any Council meeting. The Council minutes, ordinances and Planning Board records are on the township’s meeting documents pages. The explainer sets out the record in full. Corrections can be emailed to info@localwhy.org.
Timeline
- In court Greymark owner sues over the township's warehouse ordinanceAs Patch and TAPinto reported the Mayor's October 2026 letter and the owners' complaint, the owner of 1200 Route 22 sued to undo the township's October 2022 ordinance removing warehouses as a permitted principal use in certain zones. The case, SOM-L-1372-22, was described as still pending in October 2026.
- Resolved Council adopts the Greymark Redevelopment Plan, listing data centers as a permitted useOrdinance 25-05 adopted the Greymark Office Tract Redevelopment Plan for 1200 Route 22, which lists data centers as a principal permitted use. A resident's statement in the Council minutes and the owners' complaint give the adoption date as April 24, 2025; TAPinto gives April 25.
- Resolved Planning Board approves the Greymark owner's preliminary subdivisionThe Planning Board approved 1200 Route 22 Land Investors LLC's preliminary major subdivision (App. 25-021-PB) at 1210 and 1220 Route 22: four lots where five exist, one intended for a data center and three for residential use, per the Board's agenda. The resolution was memorialized 6-0 on April 21.
- Resolved Greymark repeal moved to closed session; omnibus Ordinance 26-14 introduced without data-center sectionA repeal of Ordinance 25-05 listed on an earlier agenda was moved to closed session on counsel's advice. The Council introduced the omnibus land-use Ordinance 26-14, 4-0 (Isla absent), after removing its data-center section. Ten people spoke on data centers.
- Resolved Data-center ordinance introduced; omnibus Ordinance 26-14 adoptedThe Council introduced an ordinance creating new requirements for data centers and hyperscale data centers, 4-0 (Isla absent), and sent it to the Planning Board for Sept. 1. It adopted the omnibus land-use Ordinance 26-14, 4-0, with no public speakers.
- In court Council adopts data-center standards, Ordinance #26-15, 3-0After an 11-speaker hearing, the Council adopted Ordinance #26-15, defining data centers (2 MW or more per acre) and hyperscale data centers (80 MW or more) and setting standards for any use-variance application. Bucko, Kirsh and Geiger voted aye; Isla and Ring were absent.
- In court Greymark owners sue the township over Ordinance 26-151200 Route 22 Land Investors, LLC and 1200 Route 22 Land Holdings LLC sued the township and the Planning Board in Somerset County Superior Court, asking that Ord. 26-15 be declared invalid or unenforceable in the Greymark redevelopment area, as Patch and TAPinto reported.
- Pending Council introduces #26-21, amending the Greymark planThe township's Oct. 16 notice records the introduction of Ordinance 26-21, amending the Greymark Office Tract Redevelopment Plan. TAPinto reported that the Council first struck a listed ordinance repealing the Greymark designation and plan, that both votes were 5-0, that the ordinance removes data centers as a permitted use, and that the final hearing is Nov. 5, 2026.
- Pending Planning Board finds #26-21 not inconsistent with the Master PlanAt a special meeting, the Planning Board adopted a Master Plan Reexamination Report dated Oct. 16, 2026 and found Ordinance #26-21, amending the Greymark plan, not inconsistent with the Master Plan, recommending that the Council adopt it.
Explainers
Documents
Planning Board notice of decision: Master Plan Reexamination Report (Oct. 27, 2026)
Planning Board notice of board action: master plan consistency review, Ordinance #26-21
Notice of Introduction of Ordinance 26-21: amending the Greymark ("Graymark") Office Tract Redevelopment Plan
Ordinance #26-21: amending the Greymark Office Tract Redevelopment Plan (item 26-10-15-222)
Township Council minutes, September 3, 2026: data center ordinance #26-15 adopted
Ordinance 26-14: omnibus land-use ordinance (fees, Chapter 126, residential lighting)
Township Council minutes, August 20, 2026: omnibus #26-14 adopted; data center ordinance introduced
Township Council minutes, August 6, 2026: omnibus ordinance introduced; data center language removed
Township Council minutes, July 23, 2026: 2025 audit certified; data center questions
Township Council minutes, July 9, 2026: bond ordinances #26-10 to #26-12 adopted
Township Council minutes, May 18, 2026: Whitney Court and temporary parking ordinances adopted
Township Council minutes, March 19, 2026: Water Bank note and Municipal Alliance vote
Ordinance 25-05: Greymark Office Tract Redevelopment Plan (1200 Route 22)
Meetings
- Planning Board — October 27, 2026 (special meeting)
- Township Council — October 15, 2026
- Zoning Board of Adjustment — September 22, 2026
- Township Council — September 3, 2026
- Planning Board — September 1, 2026
- Township Council — August 20, 2026
- Township Council — August 6, 2026
- Township Council — July 23, 2026
- Township Council — July 9, 2026
- Township Council — May 18, 2026
- Zoning Board of Adjustment — April 28, 2026
- Planning Board — April 21, 2026
- Township Council — March 19, 2026
- Planning Board — March 17, 2026
- Zoning Board of Adjustment — January 27, 2026
Sources for this overview
- Township Council minutes, Aug. 6, 2026 (repeal pulled; omnibus 26-14 introduced without data-center section)
- Township Council minutes, Aug. 20, 2026 (data-center ordinance introduced)
- Township Council minutes, Sept. 3, 2026 (Ordinance #26-15 adopted)
- Planning Board agenda, March 17, 2026 (App. 25-021-PB, preliminary major subdivision)
- Planning Board minutes, April 21, 2026 (25-021-PB resolution memorialized)
- Township notice of introduction of Ordinance 26-21 (Oct. 16, 2026)
- Planning Board notice of board action: master plan consistency, Ord. #26-21 (Oct. 28, 2026)
- Patch, Oct. 12, 2026: "Bridgewater Sued Over Data Center Ordinance"
- TAPinto Bridgewater/Raritan, Oct. 26, 2026: "Township to Remove Data Centers as Permitted Use at 1200 Route 22"