Planning Board — December 4, 2025
On a court-ordered remand, the Planning Board voted 5-0 to reaffirm its 2022 denial of the 107,366-square-foot Harvard Way warehouse. It also heard a progress update on the 96-unit Campus Associates apartments, 23 of them affordable.
- Development
- Litigation
- Housing
Meeting recording
Recording plays on the township archive
This meeting does not play on this page. The township's recording is complete and plays in full on the township's own channel.
What happened
What was decided
- Harvard Way JMJ4, LLC (Redcom), file 21-PB-09-MSPV (remand). The board denied this 107,366-square-foot warehouse at 3 Harvard Way off Route 206 on October 13, 2022. On February 4, 2025 the Superior Court sent limited parts of the case back to the board. After public comment and an executive session with counsel, the five eligible members voted 5-0 to affirm the denial. The reasons discussed included the soil classification and infiltration testing, the lack of a testifying witness for the NJDEP permits, and the unknown tenant. A revised resolution was to follow; it was memorialized February 5, 2026.
- Campus Associates, LLC (5 Campus Drive), a six-month update. The approved project has four three-story buildings with 96 apartments, 23 of them affordable. Site work, including stormwater facilities, was reported complete, and the applicant expected to begin leasing in summer 2026.
Adjourned 9:25 pm.