Battery storage proposed in Finderne (Rockland APV, East Main Street)
Rockland APV Bridgewater Energy LLC wants to build a lithium-ion battery energy storage system on county-owned land at East Main Street and Polhemus Lane in Finderne. As a private company it needs a use variance. The Zoning Board held a fourth hearing on Oct. 20, 2026 and has not decided.
What happens next
The Zoning Board hearing continues Nov. 24, 2026, as TAPinto reported; the Board's regular meetings are at 7 p.m., 100 Commons Way. Residents may question witnesses and comment. Application materials are open for inspection at the Land Use Administrator's office.
Rockland APV Bridgewater Energy LLC (Application 24-029-ZB) seeks preliminary and final major site plan approval and a minor subdivision for Block 338, Lot 9 (760 East Main Street), according to the township’s notice. The site, at East Main Street and Polhemus Lane in Finderne, is owned by the Somerset County Improvement Authority and used, as TAPinto described it, as a county maintenance yard; the applicant’s attorney, Glenn Pantel, told the Board on Feb. 10, 2026 that it holds an option on a long-term ground lease of a 2.892-acre parcel, with the remaining 4.235 acres staying with the county authority (Board transcript).
Why it needs a variance. Township rules allow electric storage as an “essential service” only when run by a public utility or government entity. Mr. Pantel told the Board on Feb. 10 that, as a private company, “we have acknowledged that we do need the D-1 Use Variance” (Board transcript).
What is proposed. The applicant’s chief executive, John Seker, testified on Feb. 10 to “a 20 megawatts, 80-megawatt hour Battery Energy Storage System,” able, the applicant said, to power up to 20,000 homes for four hours (Board transcript). TAPinto’s April and October reports describe it as “20,000-megawatt”; the explainer sets the figures side by side.
The hearings. The Board heard the application on Feb. 10 and July 28, 2026 (no members of the public were sworn at either, its minutes record), took it up on April 14 (its minutes record the application carried to July 28; TAPinto reported testimony that night), and heard it again at an Oct. 20 special meeting, as TAPinto reported. On July 28 the applicant’s fire consultant, Leonard Ganesh Deonarine, said the fire code “says 75 feet. What we’ve put in the emergency plan was 200 feet” (Board transcript).
What the Board has asked about. As the transcripts and TAPinto record: the tax benefit of a facility on tax-exempt county land, long-term environmental liability next to the remediated American Cyanamid site, fire risk, the 200-foot safety zone the applicant’s fire consultant recommended, and the emergency response plan, which Chairman John Kulak called lacking.
At the Council. On Feb. 5, 2026, resident Samantha Alley said the area floods and raised soil contamination concerns; Councilman Timothy Ring said the matter belongs to the Zoning Board and that the Council should not discuss its merits.
What residents can do. Attend the Nov. 24, 2026 hearing, question witnesses and comment. The explainer lists each hearing. Corrections can be emailed to info@localwhy.org.
Timeline
- Pending Battery storage application previewed at Council; resident raises flooding concernsAdministrator Pappas said the Zoning Board's Feb. 10 meeting would take up the Rockland APV lithium battery storage application in Finderne. Resident Samantha Alley cited flooding and soil contamination concerns; Councilman Ring said the matter belongs to the Zoning Board.
- Pending Zoning Board hears a 20 MW battery storage system on county landRockland APV Bridgewater Energy LLC presented a battery energy storage system on county-owned land at East Main Street and Polhemus Lane. Its attorney said a private company needs a D(1) use variance; the Board asked about taxes, liability and safety. The minutes label the session the "2nd Hearing"; no members of the public were sworn.
- Pending Battery storage hearing: fire consultant explains a 200-foot emergency-plan distanceAt the Zoning Board's hearing on Rockland APV's battery storage application (App. #24-029-ZB), engineer Craig Stires and fire consultant Leonard Ganesh Deonarine testified. No members of the public were sworn. The hearing was adjourned to Oct. 27, later moved to an Oct. 20 special meeting.
- Pending Fourth hearing on battery storage focuses on fire risk; continued to Nov. 24At a special meeting, the Zoning Board questioned the applicant's fire-safety consultant, who recommended a 200-foot safety zone. Chairman Kulak called the emergency response plan lacking. The hearing was continued to Nov. 24, 2026, TAPinto reported.
Explainers
Documents
Meetings
Sources for this overview
- Zoning Board minutes and transcript, Feb. 10, 2026 (App. #24-029-ZB)
- Zoning Board minutes, April 14, 2026
- Zoning Board minutes and transcript, July 28, 2026
- Zoning Board notice of special meeting, Oct. 20, 2026 (App. 24-029-ZB, fourth hearing)
- Zoning Board notice regarding upcoming meetings (Oct. 7, 2026)
- Township Council minutes, Feb. 5, 2026
- TAPinto Bridgewater/Raritan, Feb. 20, 2026: "Bridgewater Zoning Hears Application for Battery Energy Storage System on County Property"
- TAPinto Bridgewater/Raritan, Oct. 29, 2026: "Fire Potential Considered at Proposed Battery Storage Facility"