Franklin awarded eleven 2026 resurfacing contracts, funded largely by a May 2026 bond ordinance, and reported in October that asphalt costs had risen 36%. Residents have asked for traffic lights, crosswalks, speed humps and truck limits, including a Beekman Road petition with over 300 signatures; many of the busiest roads belong to the county or the state.

Checked against the primary record on . Every figure on this page is sourced at the foot of the article.

2026 paving under way; Manager reports asphalt costs up 36% Last moved

What happens next

The Township Council meets November 10, November 24 and December 8, 2026, 7:00 p.m., at 475 DeMott Lane; Public Discussion is open to any topic. A speed-hump ordinance was reported in progress on October 13, aiming for completion by year-end. Road problems can be reported through the township's "Report a Road Condition" form.

The township maintains its own streets. Route 27 is a state highway, and Easton Avenue, Hamilton Street and Amwell Road are county roads, so requests about them are passed to NJDOT or Somerset County rather than decided by the Council.

The 2026 paving program. Bond Ordinance 4504-26, adopted May 12, 2026 by 6–0, puts $4,650,000 into “Roads and Sidewalks”: the annual resurfacing program, crack sealing, Canal Road guiderail, stormwater upgrades, streetscape work, striping and signals. Between April 28 and September 22 the Council awarded or put on its agenda eleven resurfacing contracts with award amounts totaling $5,756,664.40 (LocalWhy’s sum). The township’s October 21 status post lists the Highwood, Sterling, Cedarbrook and Coppermine areas done, the Willow, Randolph and Golf View areas in progress, Canal Road and New Brunswick Road milling from October 26, and the Girard Avenue and Fuller Street areas for 2027. On October 13 the Township Manager “Reported a 36% increase in asphalt costs affecting paving projects.”

Safety requests. Residents asked for traffic lights on Route 27 at Princeton Highlands and at JFK Boulevard and Winston Drive, rumble strips on Amwell Road, truck signs on Weston Canal Road and Schoolhouse Road, and speed humps and crosswalks on Beekman Road, where Steven Savard presented “a petition with over 300 signatures” on June 9, 2026. The Manager said speed humps, not speed bumps, are allowed on public roads, and that a JFK–Winston warrant study was under way, with any light budgeted in 2027 if warranted. Councilman Wright reported on October 13 that a speed-hump ordinance “requiring 70% resident petition support” was in progress.

Snow removal drew more comment than any other roads subject in early 2026. The township has 45 plow routes covering over 240 miles and a $450,000-a-season contract for 22 of them.

Residents can speak at Council meetings, report road problems on the township website, send crosswalk and sign requests to the Police Traffic Safety Bureau, and take county-road requests to Somerset County Engineering.

Roads and traffic, explained

Timeline

Each dated event on this issue, oldest first, linked to the full sourced entry.

  1. Pending Regional plan lists the I-287 / Easton Avenue interchange at $97.3 millionThe NJTPA Transportation Improvement Program lists an NJDOT project (DB 9169Q) in Piscataway and Franklin to lengthen the acceleration lanes from the Easton Avenue ramps on I-287: design $7.2 million in FY2027, right-of-way $0.5 million in FY2028, construction $89.6 million in 2030–2035.
  2. Resolved Eight residents raise snow plowing and traffic lightsAfter the January storm, four residents described ice, plowing and blocked driveways, and four asked for traffic lights or studies on Route 27, JFK Boulevard and Arden and Girard. The reply: "45 plow routes cover over 240 miles," and the cost of a Route 27 light is unknown.
  3. Resolved Snow plowing contract amended to $450,000 for the seasonOn the consent agenda, 8–0, the Council amended the contract with RJM Landscaping & Design for 22 plow routes to not exceed $450,000 for the 2025–26 season (Res. 26-109). The Manager said clearing all of the township's "over 2000 bus stops" is "impossible and not practical."
  4. Resolved Cap ordinance and 2026 bond ordinances adopted, 6–0The Council adopted Ord. 4502-26 (raising the appropriation cap 3.5%), Bond Ord. 4504-26 ($8,049,100 for general improvements, including $4,650,000 for roads and sidewalks), Bond Ord. 4505-26 ($4,588,000 for the water utility) and Ord. 4506-26 ($293,500 from the Open Space Trust). No member of the public spoke at the hearings.
  5. Pending Beekman Road residents present a petition with over 300 signaturesSteven Savard, Society Hill III HOA Secretary, asked for speed bumps, crosswalks and pedestrian signals on Beekman Road and presented "a petition with over 300 signatures." The Manager said speed humps, not speed bumps, are permitted on public roads, and that speed limits need an engineering study.
  6. Resolved Route 27 resurfacing contract awarded, $168,204.10On the consent agenda, 9–0, the Council awarded "Route 27 Resurfacing (B26-011-ENG)" to Z Brothers Concrete Contractors for $168,204.10 (Res. 26-278). The resolution does not give the limits of the work. Bids were received May 28.
  7. Resolved Randolph Road and Golf View Drive paving awarded, $1.8 millionOn the consent agenda, 8–0, the Council awarded Randolph Road Area Resurfacing ($1,175,869.19) and Golf View Drive Area Resurfacing ($622,499.09) to Fischer, and renewed the 22-route snow plowing contract for 2026–27 at up to $450,000.
  8. Active King Road and Cedar Brook Drive residents speak on the water main projectFive residents of King Road, South Dover Avenue and Cedar Brook Drive spoke about the "Water Main Replacement Project." The action notes record the Manager saying a street goes on the paving list "3-6 months after a water main installed"; the township's web page says about one year.
  9. Active Manager reports asphalt costs up 36%; speed-hump ordinance in progressThe Township Manager "Reported a 36% increase in asphalt costs affecting paving projects," and Mr. Vassanella said paving faces delays. Mr. Wright reported a speed-hump ordinance "requiring 70% resident petition support, aiming for completion by the year-end."
  10. Active Township posts 2026 resurfacing status; Girard and Fuller areas set for 2027The township's status post lists the Highwood, Sterling, Cedarbrook and Coppermine areas completed; Willow, Randolph and Golf View in progress; Canal Road and New Brunswick Road milling from October 26; and the Girard Avenue and Fuller Street areas as 2027 projects.

Explainers

  • Franklin's Roads, Paving and Traffic, Explained

    Who owns which road; how the 2026 paving program is paid for and which streets it covers; the eleven resurfacing contracts and the 36% asphalt-cost report; the requests residents made for lights, crosswalks, speed humps and truck limits; Route 27 and Easton Avenue; the 2025–26 snow season; where the record's figures differ; and what residents can do.

Documents

The township's own records on this issue. Each links to the official copy.

Meetings

  • Township Council — October 13, 2026

    The Council adopted Ord. 4517-26 (cluster subdivisions) and Ord. 4520-26, the PILOT for the CWP-ASR Somerset I and II affordable-housing project at 260 Davidson Avenue, each 9-0. In Public Discussion residents spoke on the Flock license-plate cameras, the Sentinel data center in South Brunswick and the NESE project, the Davidson Avenue housing site, PILOTs, stormwater and truck traffic. Mr. Singh said he supported a full public review and a new vote on the cameras.

  • Township Council — September 22, 2026

    With six members present, the Council adopted the $1,380,000 Catalpa Park open-space ordinance 6-0 and introduced Ord. 4520-26, a PILOT financial agreement for the CWP-ASR Somerset project at 260 Davidson Avenue, 5-0. Five residents raised leaks and water pressure after the King Road and Cedar Brook Drive water main work, and seven spoke on the Flock cameras.

  • Township Council — September 8, 2026

    The Council approved a $500,000 settlement with Transco over the federal condemnation of an access easement for Compressor Station 206, on land whose development rights the Township holds, plus $100,000 for a community benefit program, 9-0. It awarded the Catalpa Park construction contract and introduced a $1,380,000 open-space ordinance for the park. Eight of 15 speakers addressed the Flock license-plate cameras.

  • Township Council — August 11, 2026

    The Public Safety Director and a Flock Safety representative presented the township's license-plate camera system, and most of the residents who spoke in Public Discussion asked about data retention, audits, cost and civil liberties, several calling for the contract to be cancelled or put to a referendum. The Council adopted the cannabis and short-term rental ordinances, introduced the cluster-subdivision ordinance 4517-26, awarded $1.8 million in resurfacing and a $1,064,962 East Millstone water main, and met in closed session on warehouse and Transco litigation.

  • Township Council — June 23, 2026

    The Council adopted the Collins Property open-space ordinances, 9-0, and introduced ordinances to acquire 287 Cedar Grove Lane for open space with $5,460,000 from the Open Space Trust Fund. The consent agenda approved a conservation partnership with the Land Conservancy of New Jersey for the Kerani property ($1,380,000) and a $168,204.10 Route 27 resurfacing contract. A Planning Board alternate nomination was tabled, 7-2.

  • Township Council — June 9, 2026

    The Council adopted Ord. 4507-26, the B-I zone ordinance limiting warehouses and removing data centers as a permitted use, 6-3, after a hearing with ten speakers. It introduced Ords. 4509-26 and 4510-26 on the 2026 master plan reexamination and the Collins Property open-space purchase, and approved a cost-share to preserve the Horses and Hay Farm. Residents presented a petition for safety measures on Beekman Road.

  • Township Council — May 26, 2026

    The Council adopted the CY2026 municipal budget as amended, 9-0, with $75,455,645.64 in appropriations and $41,722,842.00 to be raised by taxation for municipal purposes. Five residents spoke, among them one thanking the Council for limiting warehouses and banning data centers. The consent agenda carried a $325,000 guiderail repair contract and final change orders on water main and resurfacing work.

  • Township Council — May 12, 2026

    The Council introduced Ord. 4507-26, the B-I zone ordinance setting limits on warehouses, 6-0 with three members absent, after six residents spoke on warehouses and truck traffic. It adopted the 2026 general and water-utility bond ordinances, a $293,500 Open Space Trust Fund ordinance and a CAP bank ordinance, and awarded a $2,697,496 water-main replacement contract.

  • Township Council — April 28, 2026

    The agenda for the CY2026 municipal budget introduction, with a hearing set for May 26: a CAP bank ordinance (4502-26), the budget self-examination resolution and the introduction resolution, plus the 2026 general and water-utility bond ordinances and a $293,500 open-space ordinance on first reading. No minutes are posted, so no votes are reported here.

  • Township Council — April 14, 2026

    With Deputy Mayor Kharazi presiding and seven members present, the Council adopted Ord. 4501-26 vacating part of Executive Drive, which the Manager said will become a private driveway for an approved warehouse, and a temporary budget with an emergency capital appropriation, each 7-0. A resident objected to a new leaf disposal fee, and others raised traffic and crosswalk safety.

  • Township Council — March 24, 2026

    After a presentation of the 29-acre Catalpa Park plan, estimated at $9.0–$9.1 million with construction management, the Council authorized bids 8-0. Its consent agenda endorsed the Planning Board's amended Housing Element and Fair Share Plan and a $77,725 stormwater plan shared with Montgomery, and it met in closed session on the Williams Transco litigation.

  • Township Council — March 10, 2026

    The Council adopted Ord. 4496-26 on affordable housing development fees and the recycling, dog-licence and wedding-fee ordinances, each 9-0. Members reported on the 2026 road paving list, a planned review of the snow-removal ordinance, and property assessment notices with a May 1 appeal deadline.

  • Zoning Board of Adjustment — March 5, 2026

    The third night on the 258,150 sq ft warehouse proposed at 135 Davidson Avenue and the related church applications. The applicant's architect, traffic engineer and planner testified; the Planning Director noted that the site abuts a residential zone, which the B-I reexamination's draft standards would not allow; objectors' counsel argued the use variance needs an enhanced quality of proof. Carried to May 7, 7-0.

  • Township Council — February 24, 2026

    The Council adopted Res. #26-112, barring federal civil immigration enforcement from using Township-owned property without a judicial warrant or order, as amended, 8-0. It adopted the Chapter 81 affordable housing ordinance and the Castleton Park easement, the Hamilton Street SID budget and assessment roll, and a $450,000 snow-plowing contract amendment, and met in closed session on possible open-space purchases.

  • Township Council — February 10, 2026

    The Council appointed Shubhendu Singh to the vacant Ward 1 seat, 8-0, then adopted the four inclusionary zoning ordinances for the Fourth Round housing plan and the Franklin Boulevard Redevelopment Plan amendment, each 8-0, after a property owner's lawyer asked for a delay. Ten residents spoke, most on snow and ice removal and on traffic lights.

  • Township Council — January 27, 2026

    The Council introduced the CY2026 Hamilton Street Special Improvement District budget and adopted a consent agenda that included road asset management software and the 2026 county recycling pickup agreement. Members reported on the January storm response and a proposal for all-way stop signs at Hamilton and Home Streets. No member of the public spoke.

  • Township Council — January 13, 2026

    The Council ratified its settlement with Fair Share Housing Center on the Fourth Round housing plan and introduced four inclusionary zoning ordinances (MFIZ-1, -2, -4 and -5), an amendment to the Franklin Boulevard Redevelopment Plan and a water curb-connection fee ordinance, each 9-0. Three residents asked for help against the NESE project; the Council met in closed session on "Williams Transco".

  • Township Council — December 9, 2025

    On a 7-0 consent agenda the Council adopted Res. #25-511 supporting the New Jersey Immigrant Trust Act, asked the Franklin Township Sewerage Authority to transfer $100,000 to the Township budget, and set the 2026 budget hearings as remote meetings. A resident urged quick adoption of a new B-I zoning ordinance to limit warehouses.

  • Township Council — November 10, 2025

    With all nine members present, the Council's 9-0 consent agenda included an Axon "ALPR License and Integration" state contract of up to $37,800, the CY2024 audit and its corrective action plan, and two stormwater maintenance agreements. It introduced a Brookline Avenue parking ordinance and a pump-station easement. A resident raised the NESE project's air permit.

  • Township Council — October 28, 2025

    The Council designated 606–610 Franklin Boulevard and neighbouring lots (Block 233, Lots 1.01 and 2.01; Block 234, Lots 1, 14.01 and 16) an area in need of redevelopment with condemnation powers, 8-0 with Mr. Wright abstaining. It adopted Ord. 4483-25, which bars the routine use of fossil-fuel on-site generators, 9-0, and sent $10,000 in American Rescue Plan funds to the Franklin Food Bank ahead of an expected SNAP disruption.

Sources for this overview

  1. Franklin Township, "Street Resurfacing Project Status" (October 21, 2026)
  2. Township Council packet, May 12, 2026 (Bond Ord. 4504-26 and Exhibit A, pp. 54–62)
  3. Township Council minutes, May 12, 2026
  4. Township Council minutes, June 9, 2026 (Beekman Road petition; speed humps)
  5. Township Council minutes, October 13, 2026 (asphalt costs; speed-hump ordinance)
  6. Township Council minutes, February 10, 2026 (snow plowing; traffic-light requests)
  7. Somerset County, Easton Avenue (CR 527) Corridor Improvements
  8. NJTPA Transportation Improvement Program FY2026–2029, Somerset County