The short version

  • The Picket Place bridge, County Bridge No. C0609, carries County Route 567 over the South Branch Raritan River between Branchburg and Hillsborough.
  • Somerset County, coordinating with NJTPA and NJDOT, is replacing the existing four-span bridge; the project site says it is in poor condition with structural and functional limitations that do not meet today’s design standards.
  • Concept work finished in summer 2020; the site lists Local Preliminary Engineering as the current phase, dated Fall 2024 to Summer 2026.
  • Final design and right-of-way acquisition have an anticipated start in 2028; construction’s anticipated start is design-dependent.
  • The regional FY2026–2029 Transportation Improvement Program estimates the total cost at $18.616 million: $1.9 million for design in 2027, $50,000 for right-of-way in 2028 and $15.8 million for construction in 2030–2035.

What the bridge is

Somerset County’s project page identifies the bridge as County Bridge No. C0609, carrying Picket Place (CR 567) over the South Branch of the Raritan River between Branchburg and Hillsborough townships, and says the replacement addresses structural deficiencies and will conform to current AASHTO, NJDOT and county design standards. The NJTPA program says the existing bridge was built in 1979 as a four-span, simply supported prestressed concrete structure; its substructure is in poor condition, with large spalls and exposed rusted reinforcing steel, and its beams show spalls at their ends. The project website describes the bridge as in poor condition, with structural and functional limitations that do not meet today’s design standards, and calls it a transportation link for local communities and the region; it posts no closure or detour plan.

Who is doing it

Somerset County is the project sponsor, in coordination with the North Jersey Transportation Planning Authority (NJTPA) and the New Jersey Department of Transportation (NJDOT). The project runs through the federally funded Local Capital Project Delivery program, which NJDOT’s Local Aid District 3 administers: Local Concept Development, then Local Preliminary Engineering, then Final Design and Construction, with durations dependent on the improvements and on federal funding. The county says the preliminary-engineering phase is to obtain Federal Highway Administration approval of the environmental document, which qualifies the project for federal Final Design and Construction funds. The county released its request for proposals for that phase, RFP #CY-COM-9003-23, on Aug. 16, 2023. The Township does not own or run the bridge, and the Township Committee’s minutes from November 2025 through October 2026 do not take it up.

How it got here

  • May 2, 2019. Public Information Meeting No. 1, an open-house meeting at the Branchburg Municipal Building (Executive Courtroom), 5–8 p.m., to take input on the purpose-and-need statement, with print and web comment forms.
  • October 17, 2019. Public Information Meeting No. 2 at the Hillsborough Township Municipal Complex (Municipal Courtroom), 5–8 p.m., presenting conceptual improvement alternatives and taking comments on print forms.
  • Summer 2020. Local Concept Development completed; the site’s news page says the study graduated to Local Preliminary Engineering on July 1, 2020.
  • Aug. 16, 2023. The county released RFP #CY-COM-9003-23 for the preliminary-engineering phase.
  • Fall 2024. Local Preliminary Engineering listed as beginning, dated “Fall 2024 to Summer 2026.”
  • April 17, 2025. Local Officials Briefing No. 1, virtual, 10:00 a.m., to review the concept-development findings and upcoming preliminary-engineering tasks.
  • Summer–Fall 2025 (anticipated). The meetings page lists a Community Stakeholder Meeting (Summer 2025), Local Officials Briefing No. 2 (Fall 2025) and a Public Information Meeting (Fall 2025), all with time and location “TBD.” The site does not confirm whether they were held.

The schedule as published

PhaseStatus on the project site
Local Concept DevelopmentCompleted summer 2020
Local Preliminary Engineering”Current Phase: Fall 2024 to Summer 2026”
Final Design / ROW acquisitionAnticipated start 2028
ConstructionAnticipated start design-dependent

During preliminary engineering the team is to refine the preferred alternative and secure approval of the environmental document under National Environmental Policy Act requirements. The site’s timeline lists that phase’s tasks — approved cultural resources report, right-of-way report, preliminary plans, a public information meeting, the environmental document and the preliminary engineering report — without completion dates. As of Oct. 30, 2026, the project home still labeled Local Preliminary Engineering the “Current Phase: Fall 2024 to Summer 2026,” and the anticipated 2025 meetings still read “TBD.”

The budget

The NJTPA Transportation Improvement Program for FY2026–2029 lists the project as N1807, sponsored by Somerset County, classed as bridge preservation, with an estimated total project cost of $18.616 million:

PhaseFundYearAmount
DesignSTBGP-NY/NWKFY2027$1.900 million
Right-of-waySTBGP-NY/NWKFY2028$0.050 million
ConstructionSTBGP-NY/NWK2030–2035 (outside the funded four-year program)$15.800 million

The project site, separately, lists an anticipated 2028 start for final design and right-of-way acquisition.

What comes next

  • FHWA approval of the environmental document, which the county says the preliminary-engineering phase is to obtain.
  • Design funding programmed for fiscal 2027 and right-of-way funding for fiscal 2028.
  • The anticipated Community Stakeholder Meeting, Local Officials Briefing No. 2 and Public Information Meeting, still without dates on the project site.

What residents can do

  • Read the project record. The county’s project page summarizes the phase; the project website holds its maps and plans, news archive and meeting schedule.
  • Use the project’s contact channels. The site invites the public to follow and provide input on the improvements through its Get Involved page.
  • Attend the next announced project meeting when a date is posted, and ask about the preliminary-engineering status, the environmental document and any closure or detour plan.

Sources

Everything above is drawn from these. Where a source is a meeting video, the township publishes it in full.

  1. Picket Place Bridge project website (home and timeline, captured Oct. 30, 2026) (picketplacebridge.com)
  2. Picket Place Bridge project website: news (2019 meeting announcements) (picketplacebridge.com)
  3. Picket Place Bridge project website: meetings (anticipated schedule) (picketplacebridge.com)
  4. Picket Place Bridge project website: maps and plans (picketplacebridge.com)
  5. Somerset County Engineering: Picket Place Bridge - Preliminary Engineering Phase (read Oct. 31, 2026) (somersetcountynj.gov)
  6. NJTPA Transportation Improvement Program FY2026–2029, Somerset County (project N1807) (njtpa.org)

Spotted an error? Write to info@localwhy.org and we will correct it and say so.